Public Works Engineering
Thomas Weller, P.E.
| Farm to Market Road / Josh Wilson Road Intersection Improvements Francis Road Reconstruction: Section 1 Garden of Eden Rd/Willard Creek Culvert North Shore Drive Roadway Repair Upper Finney Creek  Bridge  | North Shore Drive Roadway Repair | 
| North Shore drive is caused by the following reasons, and not for lack of maintenance. No amount of maintenance could fix the root cause of the problem. Geotech investigation (Report) Causes: 
 Maintenance activities 
 According to the 2018 Geotech report, potential exits that new construction could initiate either new or historic landslides from above the road. Reconstruction of the road with retaining walls along the lakeside is the only option to restore vehicular access. Construction costs range from $3 million to $7.5million (2021 dollars). Grant fund opportunity for this road is limited due to the remoteness and a relatively low AADT (Annual Average Daily Traffic) number. Residents/lake users can help slow down erosion rate by minimizing wave energy action by reducing boat speed or limiting/restricting the use of power boats. Forming a Local Improvement District (LID) would help fund the reconstruction of this road. | 
            Project  Timelines
            
            Fall of  2018, Initial Geotechnical investigations were completed.
            
            June 2019,  an Engineering Consultant was hired to provide design solution alternatives.  Conceptual design alternatives were presented  to Skagit County for internal review and permitting agencies for informal  consultation.  The conceptual design  proposed did not garner support internally nor from permitting agencies.
            
            Summer  2019, Skagit County Public Works performed maintenance activities to prevent  continued slope failures.
            
            2019 to  2020:  Failed areas continued to  grow.  Skagit County Public Works  continued to provide maintenance activities in order to mitigate and slow the  continued failure of the slope and roadway edge, while simultaneously working  with another consultant to evaluate the expanded failures and develop appropriate  design alternatives.
            
            2020 to  present:  Slope and road conditions  continued to quickly degrade.  The extent  of failures triggered the need for significant revision to the design and it  became evident that the extent and scope of repairs had exceeded what was  originally programmed.  Revised design  alternatives were presented internally, and held another informal consultation  with WDFW on 6/24/21.
            
            July  2021:  Skagit County Public Works has  gathered enough information and would like to communicate these findings and  options to the community and general public via Public Open House to be held in  a nearby location.
            
            August 20th,  2021:  Open House at the Lake Cavanaugh  Community Hall, 5:30 pm to 6:30 pm.
,
			  
 September 14, 2021: Work session with the Skagit County Commissioners, 2:00 p.m. - 3:00 p.m.
          Funding  Sources
- Not Currently Funded
          
Contact Public Works Engineering
Assistant  County Engineer | Engineering Division Manager
            Thomas  Weller, P.E.
  
            1800 Continental Place
            Mount Vernon, WA 98273
            Phone: (360) 416-1400
            Fax: (360) 416-1405
  
            email: pw@co.skagit.wa.us



















